PROJECT LOCATION
Participating Organizations
Salini Costruttori S.p.A of Italy was entrusted to carry out the feasibility study in the Omo valley to assess the possibility of developing hydropower plant. The activities started in mid October 2005. By mid January 2006 Salini produced a Preliminary design document to be reviewed by the Client.
A memorandum of understanding has been signed between EEPCo and Salini, the Project Developer (PD) on February 2nd 2006 for the purpose of:
- Ensuring the continuation of the study;
- Producing necessary design documents for EEPCo*s review and acceptance;
- Facilitating by the PD financing arrangements with potential donors and financing agencies;
- Carry out other necessary and relevant activities.
It is envisaged that upon arranging the financing of the project, Salini could be considered as the prospective contractor for the project. The Electro Mechanical and Hydro Mechanical, Hydraulic Steel Structures works will be tendered out for international bidding by the EPC contractor on the basis of financing agencies requirements.
On July 19, 2006, EEPCo signed an Engineering Procurement (Turnkey) Contract with Salini Construttori S.p.A. of Italy for the Construction of the Gibe III Hydro-electric project.
On 22 April 2008 the Employer and the contractor signed a contract amendment due to the change in the scope of work at a total contract price of about Euro 1470( one billion four hundred seventy) million.
The quality control of the design and construction is carried out by a Joint Venture Consultant ELC Electrocosult & Coyne et Bellier is hired by the Client as Employer*s Representative.
Financing Organizations
Due to the huge investment requirement of the Project, during the negotiation of the contract with Salini, it was envisaged that, the Project could be financed by different financers. Accordingly, the following sources of finances were identified.
| No. | Type of work | Sources of Finance |
|---|---|---|
| 1 | Land acquisition and compensation | EEPCo |
| 2 | Consultancy Services Phase I 每 Pre Construction | EEPCo |
| 3 | Consultancy Service Phase II 每 during construction and Defect Liability Period | EEPCo |
| 4 | EPC Contract | |
| 4.1 | Civil Works | ? EEPCo ? National Bank of Ethiopia(NoE) |
| 4.2 | Electromechanical Works | ? ICBC(Industrial and Commercial Bank of China) |
| 4.3 | Hydraulic Steel Structures | ? ICBC(Industrial and Commercial Bank of China) |
| 5 | Administrative cost | EEPCo |
Study, Design, Construction and Supervising Organizations
Salini Construttori S.p.A. of Italy in collaboration with Studio Pietrangeli has carried out the Feasibility Study from the outset. Studio Pietrangeli acts as the EPC Contractor*s Engineer. In order to verify and confirm the acceptability of the project study and designs, EEPCo has signed a contract Agreement with a joint venture of Electro consult of Italy and Coyne Et Bellier of France to act as Employer*s Representative. Its responsibility was to carry out the review of the study and all design documents produced by the Project Developer. The JV Consultant has signed a MoU for the second phase of services. The major assignment of the Employer*s Representative includes supervision works, overall quality assurance and control of design, construction, erection, tests and commissioning works, and EPC Contract administration up to expiry of the defects liability period.
| Supervising Organizations | Activity |
|---|---|
| Ministry of Mines and Energy | Responsible Government Body for the overall project implementation |
| Ethiopian Electric Power Corporation | Project Executing Agency |
| J.V Electroconsult and Coyne Et Bellier | Employer*s Representative |
| Salini Cosrtruttori S.P.A. | Project Developer and EPC Contractor |
| Studio Pietrangeli | Contractor*s Engineer |
| CESI,Agri-Consult and Mid Day Consult | ESIA Consultant |
Project Summary
1.Major Activities of the Project
The activities in the project implementation are grouped in to two phases, namely, the pre 每 construction and construction phases.
Phase I
The major activities performed by the Project Developer and the Employer*s Representative in the first phase of the project include:
Project Developer
- Preparation of the Project Basic Design which mainly includes the performance of studies on Topography, Hydrology, Sedimentation, Geological investigations, Design Criteria, Drawings and Calculations, Implementation Planning, detailed cost estimate of the works, economical Analysis, Environmental and Social Impact Assessments and relevant mitigation measures to be implemented according to international Standards. .
- Preparation of the draft EPC Contract Documents to be signed
Employer*s Representative
- Preparation of Employer*s Requirement.
- Review of the proposal submitted by the Project Developer regarding Project design, Geological investigations, Hydrological analysis, Economical and financial analysis, Environmental Study, Review of the EPC Contract, Review of cost estimate and prepare independent update of the cost, assist EEPCo during contract negotiation.
Phase II
EPC Contractor
- Preparation of Level 1 (Final) Design
- Preparation of Level 2 (Manufacturing) Design
- Successive construction of the various components of the Project
Employer*s Representative
- Permanent control and supervision over the activities of the Contractor
- Verifying that the design and construction activities comply with optimum technical standards and the Employer*s Requirement
- Ensuring that, the project implementation is carried out within the allocated time frame.
- Overall quality assurance and control of design
- Construction, erection, tests and commissioning works
- EPC Contract administration up to expiry of the defects liability period.
2.Major Components of the Project
The main components of the Project layout are summarized as follows:- 243 meter high Roller Compacted Concrete Dam(RCC)
- An over flow crest Gated Spillway divided into nine bays controlled by hydraulically operated radial gates and designed to discharge 10,600 m3/s.
- Three diversion tunnels of 13 and 7 meter internal diameters
- An upstream pre-cofferdam and main cofferdam.
- A downstream cofferdam.
- 2 power waterways comprising intakes, power tunnels, surge shafts, penstocks and manifolds, each branching into 5 turbine inlets.
- Powerhouse on the left abutment, housing 10 Francis groups with a power of 187 MW each for a total installed power of 1,870MW.
- 10 transformers of 200 MVA installed at the back of the plant, converting the voltage from 15 kV to 400 kV.
- Substation, equipped with a double bus bar scheme from where the 400kV transmission lines start.
- In the power outlet, Intake structure with trash racks, stop logs and gates; Penstocks, Draft Tube with gates and stop logs are foreseen.
3.Technical Characteristics of the Project Components
General FeaturesThe average annual flow of the Omo River is approximately 438 m3/s and the power plant factor amounts to 0.46, corresponding to a utilization of the units of approximately 11 hours/day. The maximum/ normal operating level of the reservoir is 892 m.a.s.l., while the normal tail water level is 681 m.a.s.l. (for the total design discharge of the 10 units). The 1st unit is scheduled to start trial running generation by September 15, 2013, while all project activities are planned to be accomplished up to December 30, 2014, including the commissioning of the ten generating units.
Dam & ReservoirThe Roller Compacted Concrete Dam has an approximate height of 243 m and 610m of crest length. The dam will create a reservoir with total storage capacity of 14,700 Million m3 (with Live Storage of 11,750 Million m3 and Dead Storage of 2,950 Million m3 ). The catchment area is about 34,150 km2.
SpillwayA gated spillway is designed to discharge the following flows:
- The design flood = 10,600 m3/s(10,000 years return period)
- The exceptional flood = 18,000m3/s(probable maximum flood)
4.Implementation Schedule
The project is scheduled to be fully operational on 30/12/2014. Different milestones are set to achieve the project goal as per schedule. Some of these milestones are the following:| Description of Milestone | Scheduled Time |
|---|---|
| River Diversion in Tunnel No. 1 and 3 | April 22,2009 and June 30,2008 (accomplished) |
| Starting of Impounding | May 01,2013 |
| Starting of commissioning the first unit | September 15,2013 |
| First unit starts Trial Running Generation | September 15,2013 |
| Completion of Wet tests/Final Commissioning for all units | December,30,2014 |
| Completion of all Activities | December 30,2014 |
Project Output and Benefit
1.Physical Output
The power plant will generate on average 6,500 Gwh electrical energy per annum as and the firm production is estimated to be 6000 GWh. Its Plant Factor is worked out to be 0.46 similar to the two upstream plants. The installed capacity is 1870 MW having ten units each with the capacity of 187 MW. The generated power will be fed to the System through 400 kv transmission lines and the switchyard will have 10 units of 200 MVA transformers with five outgoing lines of 400 kv each.2.Economic Effects and Benefit
The EPC contractor has thoroughly studied the economic impact and the possible benefits to be gained from implementing the Gibe III Hydroelectric Project. Accordingly, the Economic Analyses show that, the project is economically viable and will greatly contribute to the national economy. Power export opportunities to neighbouring countries could be realized from the implementation of this project.
Representative has also endorsed the economic benefits of the project. Moreover, by implementing this project the following benefits could be harnessed.- Enhanced electric power generation capability;
- Complete satisfaction of the countries power demand;
- Reliability in the power supply;
- Foreign currency earning through selling of power to the international market;
- Meaningful economic growth to the country*s industrial development.
Resource Requirements
1.Technical Requirements
A Memorandum of Understanding (MoU) has been signed with the Project Developer for expediting the Pre-Construction activities as stipulated in section 5 above. More over a contract agreement was signed between EEPCo and the JV consultant, ELC- Electro consult & Coyne Et Bellier in order to prepare Employer*s Requirement, review of the proposal submitted by the Project Developer regarding Project design, Geological investigations, Hydrological analysis, Economical and financial analysis, Environmental Study, Review of the EPC Contract, Review of cost estimate and prepare independent update of the cost, assist EEPCo during contract negotiation.
An EPC/Turnkey Contract Agreement has been signed with SALINI COSTRUTTORI S.p.A of Italy for the construction of the Project on July 19th, 2006 followed by a MoU with the JV consultant, ELC Electroconsult & Coyne Et Bellier on Nov 7, 2006 for provision of complete quality control and supervision services. The main contract has been signed with Employer representative for construction Management and Supervision on April 2007.2.Financial Requirements
The EPC Contract amounts to Euro 1,470 million. For the Electro mechanical works 85 % in Euro and 15 % in Birr; and for Civil Works, 65% in Euro and 35% in Birr shall be paid to the Contractor. Payments for the Phase I consultancy service have been effected and amounts to Euro 0.55 Million and Birr 0.168 Million.
For the main consultancy service during the construction and defect liability periods, a contract agreement has been signed with a Joint Venture of ELC Electro consult and Coyne et Bellier Consultant at a cost of Euro 20.9 Million and Birr 17.8 Million. A running cost for the Project Coordination office is estimated to be Birr 20 Million for the period of the project. A panel of Experts engaged to ensure absolute guarantee on the implementation of the project.3.Financial Plan & Possible Financial Sources
EEPCo is not in a position to solely finance the Gibe III Hydroelectric Project Construction cost, which is very huge, thus, all efforts underway both from Employer and contractor to get fund from potential donors.Total Project construction cost - Euro 1,470 Million
Local Currency Component of - Euro 448 M (Amount of LC Disbursed to date - ?196.33 M))
Foreign Currency Component of - Euro 1022 M (Amount of FC Disbursed to date- ? 261.75M)
| IDENTIFIED FINANCING SOURCES | AMOUNT (M Euro) |
|---|---|
| AfDB (Electro mechanical Equipment) | 250 |
| AfDB (Electro mechanical Equipment) | 100 |
| Government of Italy (civil Works) | 250 |
| AfDB(Private Window) | 100 |
| Sub 每 Total | 700 |
EEPCo/National Bank of Ethiopia (Amount of FC Disbursed to date) Local Currency Disbursed to date |
211 210 |
| Total | 911 |
| Grant/Concessional Loan/Government Equity/Commercial Loan | 111 |
| Foreign Currency Grand Total | 1022 uro |

