Power SDP - Cost Estimate and Financing

Introduction | Energy Policy | Program Objectives | Program Summary | Cost Estimate & Financing
Implementation Strategy

 

Cost Estimate and Financing
  1. Cost Estimate
The total investment of the PSDP is Birr 8,271 million (equivalent to USD 994 million at 1USD=Birr 8.323).  A summary breakdown of the cost components of the program is given as follows:

 

Investment Breakdown  (In million Birr) (2000/01 - 2004/05)
Table 6
No. Sub-program component L/C F/C Total Share in %
1 Generation 1,444 3,792 5,236 63
2 Power Transmission 470 1,200 1,670 20
3 Distribution and Rural Elec. 270 535 805 10
4 Institutional 326 234 560 7
Total 2,510 5,761 8,271 100.0
Fiancing Plan
Table 7
No. Source Amount Share in %
1 Loan 984.0 12
2 Grant 35.0 -
3 Equity 413.0 5
4 EEPCO 2,893 35
5 Other Sources * 3,946 48
Total 8,271 100.0
* It could be from bilateral grants/loans or additional loans or suppliers credit or revision of tariff.
  1. Financing and Strategy

The PSDP implementation requires financing of varying degrees. Looking at the investment breakdown of the program it can be seen that the largest single sum is one that is required for the generation subprogram, followed by transmission, distribution and rural electrification. Since the financial requirement of the sector is of immense magnitude a single source could not possibly raise the full financing requirement. This being the reason various international donors are expected to be mobilised to fill the gap over and above what could be locally raised in order the government be able to meet the service demanded by the growing economy and electrify the urban and rural areas of the country.

The PSDP with a total cost of Birr 8,271 million (USD 993 million) including for ongoing projects is expected to be parallel financed by the World Bank, European Investment Bank, Nordic Development Bank, Agency Franciase De Development, Austria Development Agency and Arab Bank. Total external financing amounts to Birr 2,857 million out of which Birr 900 million is secured and Birr 1,957 million is not yet secured. The Government, EEPCo and electricity users are expected to contribute Birr 5,122 million.

Contact Us:
Ethiopian Electric and Power Corporation (EEPCo)
P.O.Box 1233 Tel. 251-01-560042
Fax : 251-01-550822 E-mail: eelpa@telecom.net.et
 

Introduction | The Energy Policy | Program Objectives | Program Summary | Cost Estimate & Financing
Implementation Strategy

 

Page Last Updated November 21, 2002


Copyright©2002 Ethiopian Electric and Power Corporation (EEPCo).
All rights reserved.