- Cost Estimate
|
| The total investment of the PSDP is Birr
8,271 million (equivalent to USD 994 million at 1USD=Birr 8.323). A summary
breakdown of the cost components of the program is given as follows: |
|
| Investment
Breakdown (In million Birr) (2000/01 -
2004/05) |
| Table 6 |
| No. |
Sub-program component |
L/C |
F/C |
Total |
Share in % |
| 1 |
Generation |
1,444 |
3,792 |
5,236 |
63 |
| 2 |
Power Transmission |
470 |
1,200 |
1,670 |
20 |
| 3 |
Distribution and Rural Elec. |
270 |
535 |
805 |
10 |
| 4 |
Institutional |
326 |
234 |
560 |
7 |
| Total |
|
2,510 |
5,761 |
8,271 |
100.0 |
|
|
| Fiancing Plan |
Table 7
| No. |
Source |
Amount |
Share in % |
| 1 |
Loan |
984.0 |
12 |
| 2 |
Grant |
35.0 |
- |
| 3 |
Equity |
413.0 |
5 |
| 4 |
EEPCO |
2,893 |
35 |
| 5 |
Other Sources * |
3,946 |
48 |
| Total |
|
8,271 |
100.0 |
|
| * It
could be from bilateral grants/loans or additional loans or suppliers credit or revision
of tariff. |
|
- Financing and Strategy
|
The PSDP implementation requires financing of varying degrees.
Looking at the investment breakdown of the program it can be seen that the largest single
sum is one that is required for the generation subprogram, followed by transmission,
distribution and rural electrification. Since the financial requirement of the sector is
of immense magnitude a single source could not possibly raise the full financing
requirement. This being the reason various international donors are expected to be
mobilised to fill the gap over and above what could be locally raised in order the
government be able to meet the service demanded by the growing economy and electrify the
urban and rural areas of the country.
The PSDP with a
total cost of Birr 8,271 million (USD 993 million) including for ongoing projects is
expected to be parallel financed by the World Bank, European Investment Bank, Nordic
Development Bank, Agency Franciase De Development, Austria Development Agency and Arab
Bank. Total external financing amounts to Birr 2,857 million out of which Birr 900 million
is secured and Birr 1,957 million is not yet secured. The Government, EEPCo and
electricity users are expected to contribute Birr 5,122 million. |
|
|
|
|